Pitts Wilson were appointed as a nominated sub contractor for the design and installation of services to this new food production facility in Bradford.

Pitts Wilson provided the site’s High Voltage 4MVA network with cable switchgear and transformer installation. From this network an extensive sub main distribution system, complete with departmental metering was installed to provide local protection of circuits (An interesting installation due to the extremes of areas including freezers, ovens, wet areas and both low level and high level installation areas). The addressable fire alarm system was another complex installation with the differing areas involving the need for a VESDA system to part of the facility.

The ongoing systems are serviced and maintained by our Maintenance and Support Services engineers.